Saturday, July 11, 2009



More rows added. Kind of grows on you, doesn't it.

May 30, 2009

Seven feet up. Forms for windows and doors added.

May 30, 2009


Scaffolding in place. Going up to ten feet high.

June 6, 2009

Cutting and installing rows of blocks.

June 6, 2009


Framing members and rebar hold the blocks in place. Waiting for the cement.

June 15, 2009


Cement pumper arrives.

June 17, 2009


Cement is pumped into the ICF blocks.

June 17, 2009

Management...? Or are we just on break... Rob Andersen and Tom Barnes discuss details on the plans.

June 6, 2009


Kate Deras - the new homeowner.

June 13, 2009

Ledger boards are mounted around the inside perimeter.

June 20, 2009


The main beam is leveled. Four are fastened together in a sandwich.

June 20, 2009


The main beam going up. Kate approves.

June 20, 2009